Light weight steel solution accelerated frame build time by 28%

Illustration

Project Summary

• Sector: Aged Care• Project Name: Infin8 Mt Lofty• Location: Toowoomba, QLD• Project Total Cost: $30 million• Developer/ Principal: Infin8 Care• Builder: Woollam Constructions• Architect: Gary J. Garnett and Associates
• Engineer: ADG• AFS Project Team: Karl Blomfield, Senior Detailer; Nick Addison, Construction Manager; Sean Warren, Detailer
• Project Goal: To design and construct a 4,600m² 3-level aged care building.
• Principal AFS Products: Wall framing, structural framing, roof trusses, ceiling panels all made from TRUECORE® steel, and other structural steel beams.• Complete Project Timeframe: 18 months

Infin8 Mount Lofty is the developer’s first new generation facility in Australia. The building spans 4,600m2 and has 134-beds for residents, with all rooms containing a private ensuite and some featuring a balcony. The facility also has a specialised 32-bed memory support unit.

The building sits on an elevated 2-acre lot taking in views of the adjacent sporting oval through to the city landscape.

The facility has been designed in a figure eight, over three levels, with four wings. Two levels are dedicated to resident accommodation. The other level is dedicated to communal areas including: dining, lounge, wellness centre, hair and beauty salon, barista café, theatre room, and function area. The facility also has a welcoming foyer, office, kitchen, laundry, maintenance, service and staff zones.

Australian Framing Solutions (AFS) drew from its breadth of experience in delivering complex, high-profile projects to enable the team to engineer several successful solutions at Infin8 Mount Lofty that allowed greater efficiencies for the project, builder, and follow-on trades.

Challenges

    The project was a complex 4-storey, figure 8 (infinity) design.
    Difficult roof design - low pitched with insufficient mechanical clearance, complex hip and valley sets through the twin octagonal structure, and integration of blockwork and other structural elements.
    Third party pre-fabricated bathroom pods required cranage and installation after AFS framing was completed and before the roof was built.
    Limited space on site required perfectly orchestrated delivery.
    Time-critical construction with no flexibility as residents expected to move in at program conclusion.
    Limited availability of suitable local resources.

Consultation and Collaboration

Detailed consultation with project stakeholders was required to ensure thedesign and construct offer met all the expectations of the builder and architect.
Specific collaboration and coordination with Woollam Constructions, the third-party bathroom pod supplier, and other trades were required to establish precise requirements and timeframes for the pods.
Ongoing communication was critical to manage logistics, meet crane requirements, and ensure the build schedule was met.

The Solutions

By utilising AFS’s 3D Scottsdale design and engineering software, the teamtransformed the original heavy structural design into a lightweight frame solution which accelerated design, manufacture, and installation time by more than 28% of the original intent.
AFS delivered a unique roof design that utilised a traditional truss system andpanelised products. The design allowed architectural intent to be achieved and also increased space for mechanical services to run through the structure. This enabled trades to easily access the area during installation and later, for maintenance.
As AFS light weight steel walls needed to be installed prior to the pre-manufactured bathroom pods which required cranage for installation, the design demanded accuracy, to the millimeter.
AFS engineered the design to allow the surrounding firewalls to fit seamlessly, which in turn enabled Woollam Constructions to complete the building to code.
To deliver the large volume of frames, AFS utilised its Brisbane-based factories to manufacture. Supply of product to site was coordinated via its purpose-built transportation vehicles. There was limited space on site which required just-on-time deliveries as needed by installers.
Thanks to AFS’s experience in complex logistics, deliveries were well-timed, fitting in with the construction schedule and crane requirements.
AFS operates in a socially responsible way and always attempts to engage the local workforce where it is delivering projects. On this occasion, AFS combined a mix of local tradespeople, managed by and supplementing AFS’s own crew, to deliver the installation.

Outcomesand Results

AFS achieved practical completion in 30 days from delivery with a further two days for final engineer sign off.
The project was delivered in full, on time, and under budget. Residents of Infin8 were able to move in at the expected time. AFS met all complex project requirements including engineering an improved roof design to allow efficiencies for trades, both during construction and maintenance intothe future.
The AFS team enabled a seamless integration of the pre-fabricated bathroompods which were installed successfully.

Feedback

Alex Duffy

Project ManagerCondev Constructions

Joe Finocchiaro

Sunland Construction ManagerSunland Developments

Rick Rowntree

Project ManagerHutchinson Builders

People, Partnerships & Progress

People & Experience

Our team has developed framing methods that deliver more large-scale projects simultaneously than any other company in the country.
.

Partnerships Built On Trust

We believe trust goes further than the stability of the frame, it's also about the company that’s delivering it - that’s why our promise is to be consistent on price, quality and always deliver.

Progress & Vision

We are driven by a deep passion for our industry. We have fostered a culture hinged on an attitude - always show up and never give up.

We Partner With

Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo
Partner logo